Mansard Conversion

Beech Grove

Sunningdale, Berkshire · 2022

A painted-timber mansard conversion to a 1930s villa, delivering two guest bedrooms, a shared bathroom and a compact study perched over the garden.

Beech Grove — Mansard Conversion
Type
Mansard Conversion
Added floor area
560 sq ft
Bedrooms added
2
On site
13 weeks

The brief

A retired couple wanted room for visiting grandchildren without extending outwards into their much-loved garden. The brief specifically asked for rooms that felt 'like a small country hotel — proper rooms, not spare rooms'.

The challenge

The 1930s roof form was fussy, with multiple hips and valleys. A dormer would have looked pinched; a full mansard risked overwhelming the house. The garden could not be compromised, which ruled out any temporary works or material storage at the rear.

Our response

We designed a painted timber mansard, detailed as if it had always been there — deep eaves, generous cills, and a slate cheek that folds neatly into the existing roof. Interior finishes were chosen for warmth: paneled walls, wool carpet, and soft brass. The study is a small folly at the top of the stairs, with a single dormer window framing the beech tops.

Location & context

Beech Grove is a 1930s villa on a leafy road in Sunningdale, backing onto a mature garden bordered by beech trees. The road is characterised by a rhythm of similar houses with careful, understated additions — a context that rewards restraint.

The project, in full

How it came together.

The mansard was drawn to sit within the existing envelope of the roof, rather than above it. From the road, only the two carefully-placed sash windows give it away; from the garden, the painted timber reads as a natural extension of the existing weatherboard porch.

All materials were delivered through the front of the house and lifted over the roof by a small crane on the driveway, in three carefully-planned days. Not a paving stone in the garden was disturbed.

The panelled interior was designed with the client's antique furniture in mind. The wall heights, the panel proportions and even the picture-rail heights were dimensioned so that a particular pair of inherited wardrobes would sit centred beneath the window in each guest room.

Gallery

A quiet walk through the finished home.

Beech Grove front elevation at dusk with new slate mansard and traditional dormer sashes
Front elevation at dusk — new mansard sitting quietly on the 1930s villa
Guest bedroom under the mansard with painted panelling, dormer sash and antique wardrobe
Guest bedroom — panelled, warm, a proper room
Shared guest bathroom with roll-top cast-iron bath, brass telephone taps and dormer sash
Shared bathroom — roll-top bath under the dormer
Compact study at the top of the stairs with a single dormer window framing the beech tops
The study — a small folly over the garden
Construction stage showing the new mansard timber frame being clad in slate and painted timber
Mid-build — mansard framed, slate going on, garden untouched

Materials & finishes

  • Painted timber cladding
  • Natural Welsh slate
  • Traditional lead flashings
  • Wool loop-pile carpet
  • Bespoke paneled joinery
  • Cast-iron radiators (restored)
  • Solid brass door furniture

Services delivered

  • Architectural design
  • Planning and building control
  • Structural engineering
  • Party wall coordination
  • Full build and project management
  • Bespoke panelling and joinery
  • Interior finishing

Programme

13 weeks on site.

Design and consents ran ahead of the build; the on-site programme was planned week by week.

  1. 01

    Design and planning

    10 weeks
  2. 02

    Structural design and party wall

    5 weeks
  3. 03

    Strip-out and structure

    2 weeks
  4. 04

    Mansard, slate and weathering

    3 weeks
  5. 05

    First fix and plaster

    3 weeks
  6. 06

    Panelling, joinery and finishing

    5 weeks

Sustainability

The mansard timber was sourced from an FSC-certified Scandinavian mill and painted with a low-VOC linseed-based system chosen for a fifteen-year maintenance interval. Insulation levels significantly exceed Building Regulations, improving the whole-house EPC by two bands.

Credits

Design and delivery
Elisha Homes
Structural engineer
Thames Valley Structures
Joinery and panelling
In-house workshop
Slating and leadwork
Berkshire Heritage Roofing

In the client's words

The grandchildren asked if we'd always had a top floor. That, to us, is the highest compliment.
Mr & Mrs D. · Homeowners, Sunningdale